Project Management - An Insight on Indian IT Industry
Sidhant Kumar
Author:Sidhant Kumar
Team leader
IT Project Risk Management Process - A Practical and Effective Approach
Wednesday 25th, June 2008

It is said that a strong risk management process can decrease problems on a project by as much as 80 or 90 percent. In combination with solid project management practices having a well-defined scope, incorporating input from the appropriate stakeholders, following a good change management process, and keeping open the lines of communication a good risk management process is critical in cutting down on surprises, or unexpected project risks. Today, one cannot deny from the fact that such risk management process can help in problem resolution.

However, there are certain steps whose absence can affect project risk management process. Here are seven-step risk management processes that can be effectively utilized to accomplish desired project result.

Step 1: Each person involved in the planning process individually list at least ten potential risk items. Often with this step, team members will assume that certain project risks are already known, and therefore do not need to be listed. For example, scope creep is a typical problem on most projects. Yet it still must be listed because even with the best practice management processes in place, it could still occur and cause problems on a project over time. Therefore it should be addressed rather than ignored.

Step 2: Collect the lists of project risks and compile them into a single list with the duplicates removed.

Step 3: Assess the probability, the consequence and the detect-ability of each item on the master list. This can be done by assigning each item on the list a numerical rating such as on a scale from 1 to 4 or a subjective term such as high, medium, or low. Detect-ability is optional, but it can be simple to assess if a risk is harder to see, such as with scope creep, then it's a riskier item. If it's easier to catch early, such as loss of management support or loss of a key resource, then it's lower risk.

Step 4: Break the planning team into subgroups and to give a portion of the master list to each subgroup. Each subgroup can then identify the triggers warning signs for its assigned list of project risks.

Step 5: Subgroups must be able to identify possible preventive actions for the threats and enhancement actions for the opportunities.

Step 6: At this stage the subgroups must create a contingency plan that should includes the actions one would take if a trigger or a risk were to occur. This plan has to be created for those risks scoring above a certain cut-off point, which are determined after looking at the total scores for all risks.

Step 7: Determine the owner of each risk on the list. The owner is the person who is responsible for watching out for triggers and then for responding appropriately if the triggers do in fact occur by implementing the pre-approved and now established contingency plan. Often, the owner of the risk is the project manager, but it is always in the best interest of the project for all team members to watch for triggers while working on the project.

Often, the steps in which triggers and preventive actions are identified are overlooked. However, these are vital to the entire risk management process. After a team has completed this exercise once, the members will be better conditioned on what to pay attention to while managing the project so they are more proactive in catching changes or issues early. If these steps in the risk management process are skipped, the team can find themselves in constant reaction mode, simply implementing a contingency plan for each risk after that risk catches them by surprise.

A risk management process does not have to be complicated or time consuming to be effective. By following a simple, tested, and proven approach that involves seven steps taken at the beginning of each project the project team can prepare itself for whatever may occur.

 
Comments
Comment 1: By shilp rai on 28th Jun 2008
Apart from risk management although it is ultimate tool to optimize the feasibility and results, people management and game theory also works simultaneously when you are dealing among group and lead them. As there are many dicrpencies could be generated during handling a project like conflicts, depression, lack of time management by anyone etc so to manage the people in the group is very much needed and knowingly or unknowingly we are managing the people anyhow but there must be a way to deal every situation like there are laws of persuasions which acts simultaneously when u are dealing with people and convience them and just like it to make according strategies dor the project execution game theory work as catalyst like prisioners dilemma as a case and economical part also supports the smooth and pefect forecasted execution of projet so its a type of illuminati sapphire which is crowned the project ultimately

Comment 2: By George Manuval on 27th Jun 2008
I agree with Satish Desai. Take a live example of recent tsunami in Asian sub-continent. Risk Management measures are being implemented. However, are there any proper risk assessment plans? If it was in place, the risks could have been reduced upto a certain extent.



Comment 3: By Sidhant Kumar on 27th Jun 2008
Thanks for your feedback

Comment 4: By SATISH DESAI on 27th Jun 2008
Risk management is often fictitious and done for the sake of procedure. Risk assessment is the first important item and this requires a clear idea of the hazard (its magnitude and nature) and probability of its occurrence. Probability assessment must have reliable and sufficient statistical data, which is often not avialable. The so-called risk assessment and its management is based on guesswork, routine assumptions and extrapolation of meagre data, which may generate a large volume of paperwork with a comparatively low value-for-money. The best one can usefully achieve is hazard identification. I have known people who misuse the word "risk", while all they mean is "hazard". Any ill-founded risk management exercise carries the possibility of stifling innovation and use of lateral thinking.

Post your valuable comment here
Email:      Password:  
Don't have SiliconIndia ID? Sign up      Forgot your Password?  Retrieve

 Latest postings

Insight on PMP Certification
There are many professionals who endeavor to gain as many certifications as possible and others who try hard to attain the highest certification possi... more >>
The Rising Need of Project Management Training
In today’s global marketplace, complexity and speed are essential factors to survive. If we try to have close look on different projects taking pl... more >>
Project Management Knowledge Areas
Project management is a critical skill required for execution. It is an essential organizing and managerial discipline in getting things done. In fact... more >>
Project Management in IT Industry
Managing an IT project is not an easy job and today it is just like a juggling chunk of Jell-O. Information technology is especially slippery because ... more >>
Top Industries to Start and Grow your Business
Internet Services, Data Processing and other Information Services Today, 850 million computers exist worldwide, 71% more than in 2000, according t... more >>
More postings 1  2  3    next >>

Editors choice

E Governanace & India
E-Governance is the use of information and communication technolo... more >>
By
Ashish Kumar
SEO & Link Building Tips
Free SEO & Link Building Tips Domain Names The first th... more >>
By
Mohan kumar
WHERE DO YOU KEEP YOUR MOBILE PHONE?
At the rate at which we are going, we might have to live life li... more >>
By
ravi kanth
E2K !!!
Barely a day goes by without a headline about the impact of CO2 e... more >>
By
Neeraj Bhushan
Changing India - Step I
Dear Friends, Thanks to all of you for an overwhelming response ... more >>
By
Shantanu Satyameva Jayate

Guest contributors

Vineet Nayar
Vineet Nayar
CEO, HCL Technologies
Rajendra K Misra
Rajendra K Misra
Author is the founder of Change India
Narayana Murthy
Narayana Murthy
Chairman & Chief Mentor, Infosys Technologies.
Sridhar Jayanthi
Sridhar Jayanthi
Vice President of Engineering and Head of India Operations, McAfee
Vikram Shah
Vikram Shah
President - India Operations, NetApp.
 Our sponsors